Change Management

Infographic - 30 Impacts of a Change Request

 

Use this when assessing your next change request!

change-request-1.jpg

change-request-2.jpg

change-request-3.jpg

 

About the Author

Jamal Moustafaev, MBA, PMP – president and founder of Thinktank Consulting is an internationally acclaimed expert and speaker in the areas of project/portfolio management, scope definition, process improvement and corporate training. Jamal Moustafaev has done work for private-sector companies and government organizations in Canada, US, Asia, Europe and Middle East.  Read Jamal’s Blog @ www.thinktankconsulting.ca

Jamal is an author of three very popular books: 

Cheat Sheet - How to Assess the Impact of the Change Request?

 

You have assembled either your entire project team or at least all of the technical team leads from different areas. The job of these people is to assess the combined impact of the new change request on key dimensions of your current project: scope, time, budget, duration and quality. What are questions that should be asked in order to accomplish this task (see Figure 1)?

Figure 1

ChangeRequestQuestions.JPG

Question: What important cost and effort ingredient was omitted from the table above?

Answer: The “cost of assessing” the Change Request, irrelevant to whether it was or was not approved!

Conclusion: Educate your project stakeholders that they are delaying your project and potentially increasing the costs EVERY time they submit a change request irrelevant of whether it was approved or rejected! Assessing the requested change is an expensive and time-consuming task.

About the Author

Jamal Moustafaev, MBA, PMP – president and founder of Thinktank Consulting is an internationally acclaimed expert and speaker in the areas of project/portfolio management, scope definition, process improvement and corporate training. Jamal Moustafaev has done work for private-sector companies and government organizations in Canada, US, Asia, Europe and Middle East.  Read Jamal’s Blog @ www.thinktankconsulting.ca